Sign up to the MySalford newsletter and don't miss a thing happening in and around the city Roadworks around Salford precinct which were delayed due to Covid will cost 40 pc more than first agreed - with the local authority having to hand over an extra £1.2m.
The work on Hankinson Way, Rossall Way and the subways around Salford Shopping Centre started in September 2019 and were due to last 12 months.
But contractor Eurovia claims it has incurred extra costs needed to cover a drainage redesign, additional structural works to the subways and tackling Japanese Knotweed, taking the total price of the Pendleton project to £4.4m.